CPMGT 302 Risk Identification Scenarios

Scenario One:

A retail firm has a project that is focused on expansion into third-world countries to sell pharmaceutical products. The project timeline is, as always, aggressive. The scope is well documented and understood by the project team and key members of the firm. The firm is financially sound, with project funds secure; however, the stakeholders expect that the project will pay for itself within 2 years of deployment.

Scenario Two:

A construction company has been awarded the contract to build a pipeline in Alaska. The project timeline is of the highest priority because work can only be completed during summer months due to adverse weather conditions. One of the suppliers of a key component has longer lead time than is required to complete the pipeline, but may be able to deliver if the construction company will pay fees to expedite. There are other suppliers, but these suppliers are not on the construction company’s approved suppler list and it would take time to get them approved. There is a huge penalty in the contract if the project is not completed on time.

Scenario Three:

A telecommunications company has just assigned you to be project manager for a product improvement project. The scope statement of the project simply says, “Make this product better.” The engineering team believes that they know how to make the product better and have ignored ideas from the sales team. The project funds are secure, as the company believes that improving this product will give them strategic advantages.

Previous answers to this question


This is a preview of an assignment submitted on our website by a student. If you need help with this question or any assignment help, click on the order button below and get started. We guarantee authentic, quality, 100% plagiarism free work or your money back.

order uk best essays Get The Answer
Uncategorized

Leave a Reply

Your email address will not be published. Required fields are marked *

CPMGT 302 Risk Identification Scenarios

Scenario One:

A retail firm has a project that is focused on expansion into third-world countries to sell pharmaceutical products. The project timeline is, as always, aggressive. The scope is well documented and understood by the project team and key members of the firm. The firm is financially sound, with project funds secure; however, the stakeholders expect that the project will pay for itself within 2 years of deployment.

Scenario Two:

A construction company has been awarded the contract to build a pipeline in Alaska. The project timeline is of the highest priority because work can only be completed during summer months due to adverse weather conditions. One of the suppliers of a key component has longer lead time than is required to complete the pipeline, but may be able to deliver if the construction company will pay fees to expedite. There are other suppliers, but these suppliers are not on the construction company’s approved suppler list and it would take time to get them approved. There is a huge penalty in the contract if the project is not completed on time.

Scenario Three:

A telecommunications company has just assigned you to be project manager for a product improvement project. The scope statement of the project simply says, “Make this product better.” The engineering team believes that they know how to make the product better and have ignored ideas from the sales team. The project funds are secure, as the company believes that improving this product will give them strategic advantages.

Previous answers to this question


This is a preview of an assignment submitted on our website by a student. If you need help with this question or any assignment help, click on the order button below and get started. We guarantee authentic, quality, 100% plagiarism free work or your money back.

order uk best essays Get The Answer
Uncategorized

Leave a Reply

Your email address will not be published. Required fields are marked *